Keep Us Strong WikiLeaks logo

Currently released so far... 251287 / 251,287

Articles

Browse latest releases

Browse by creation date

Browse by origin

A B C D F G H I J K L M N O P Q R S T U V W Y Z

Browse by tag

A B C D E F G H I J K L M N O P Q R S T U V W X Y Z
AEMR ASEC AMGT AE AS AMED AVIAN AU AF AORC AGENDA AO AR AM APER AFIN ATRN AJ ABUD ARABL AL AG AODE ALOW ADANA AADP AND APECO ACABQ ASEAN AA AFFAIRS AID AGR AY AGS AFSI AGOA AMB ARF ANET ASCH ACOA AFLU AFSN AMEX AFDB ABLD AESC AFGHANISTAN AINF AVIATION ARR ARSO ANDREW ASSEMBLY AIDS APRC ASSK ADCO ASIG AC AZ APEC AFINM ADB AP ACOTA ASEX ACKM ASUP ANTITERRORISM ADPM AINR ARABLEAGUE AGAO AORG AMTC AIN ACCOUNT ASECAFINGMGRIZOREPTU AIDAC AINT ARCH AMGTKSUP ALAMI AMCHAMS ALJAZEERA AVIANFLU AORD AOREC ALIREZA AOMS AMGMT ABDALLAH AORCAE AHMED ACCELERATED AUC ALZUGUREN ANGEL AORL ASECIR AMG AMBASSADOR AEMRASECCASCKFLOMARRPRELPINRAMGTJMXL ADM ASES ABMC AER AMER ASE AMGTHA ARNOLDFREDERICK AOPC ACS AFL AEGR ASED AFPREL AGRI AMCHAM ARNOLD AN ANATO AME APERTH ASECSI AT ACDA ASEDC AIT AMERICA AMLB AMGE ACTION AGMT AFINIZ ASECVE ADRC ABER AGIT APCS AEMED ARABBL ARC ASO AIAG ACEC ASR ASECM ARG AEC ABT ADIP ADCP ANARCHISTS AORCUN AOWC ASJA AALC AX AROC ARM AGENCIES ALBE AK AZE AOPR AREP AMIA ASCE ALANAZI ABDULRAHMEN ABDULHADI AINFCY ARMS ASECEFINKCRMKPAOPTERKHLSAEMRNS AGRICULTURE AFPK AOCR ALEXANDER ATRD ATFN ABLG AORCD AFGHAN ARAS AORCYM AVERY ALVAREZ ACBAQ ALOWAR ANTOINE ABLDG ALAB AMERICAS AFAF ASECAFIN ASEK ASCC AMCT AMGTATK AMT APDC AEMRS ASECE AFSA ATRA ARTICLE ARENA AISG AEMRBC AFR AEIR ASECAF AFARI AMPR ASPA ASOC ANTONIO AORCL ASECARP APRM AUSTRALIAGROUP ASEG AFOR AEAID AMEDI ASECTH ASIC AFDIN AGUIRRE AUNR ASFC AOIC ANTXON ASA ASECCASC ALI AORCEUNPREFPRELSMIGBN ASECKHLS ASSSEMBLY ASECVZ AI ASECPGOV ASIR ASCEC ASAC ARAB AIEA ADMIRAL AUSGR AQ AMTG ARRMZY ANC APR AMAT AIHRC AFU ADEL AECL ACAO AMEMR ADEP AV AW AOR ALL ALOUNI AORCUNGA ALNEA ASC AORCO ARMITAGE AGENGA AGRIC AEM ACOAAMGT AGUILAR AFPHUM AMEDCASCKFLO AFZAL AAA ATPDEA ASECPHUM ASECKFRDCVISKIRFPHUMSMIGEG
ETRD ETTC EU ECON EFIN EAGR EAID ELAB EINV ENIV ENRG EPET EZ ELTN ELECTIONS ECPS ET ER EG EUN EIND ECONOMICS EMIN ECIN EINT EWWT EAIR EN ENGR ES EI ETMIN EL EPA EARG EFIS ECONOMY EC EK ELAM ECONOMIC EAR ESDP ECCP ELN EUM EUMEM ECA EAP ELEC ECOWAS EFTA EXIM ETTD EDRC ECOSOC ECPSN ENVIRONMENT ECO EMAIL ECTRD EREL EDU ENERG ENERGY ENVR ETRAD EAC EXTERNAL EFIC ECIP ERTD EUC ENRGMO EINZ ESTH ECCT EAGER ECPN ELNT ERD EGEN ETRN EIVN ETDR EXEC EIAD EIAR EVN EPRT ETTF ENGY EAIDCIN EXPORT ETRC ESA EIB EAPC EPIT ESOCI ETRB EINDQTRD ENRC EGOV ECLAC EUR ELF ETEL ENRGUA EVIN EARI ESCAP EID ERIN ELAN ENVT EDEV EWWY EXBS ECOM EV ELNTECON ECE ETRDGK EPETEIND ESCI ETRDAORC EAIDETRD ETTR EMS EAGRECONEINVPGOVBN EBRD EUREM ERGR EAGRBN EAUD EFI ETRDEINVECINPGOVCS EPEC ETRO ENRGY EGAR ESSO EGAD ENV ENER EAIDXMXAXBXFFR ELA EET EINVETRD EETC EIDN ERGY ETRDPGOV EING EMINCG EINVECON EURM EEC EICN EINO EPSC ELAP ELABPGOVBN EE ESPS ETRA ECONETRDBESPAR ERICKSON EEOC EVENTS EPIN EB ECUN EPWR ENG EX EH EAIDAR EAIS ELBA EPETUN ETRDEIQ EENV ECPC ETRP ECONENRG EUEAID EWT EEB EAIDNI ESENV EADM ECN ENRGKNNP ETAD ETR ECONETRDEAGRJA ETRG ETER EDUC EITC EBUD EAIF EBEXP EAIDS EITI EGOVSY EFQ ECOQKPKO ETRGY ESF EUE EAIC EPGOV ENFR EAGRE ENRD EINTECPS EAVI ETC ETCC EIAID EAIDAF EAGREAIDPGOVPRELBN EAOD ETRDA EURN EASS EINVA EAIDRW EON ECOR EPREL EGPHUM ELTM ECOS EINN ENNP EUPGOV EAGRTR ECONCS ETIO ETRDGR EAIDB EISNAR EIFN ESPINOSA EAIDASEC ELIN EWTR EMED ETFN ETT EADI EPTER ELDIN EINVEFIN ESS ENRGIZ EQRD ESOC ETRDECD ECINECONCS EAIT ECONEAIR ECONEFIN EUNJ ENRGKNNPMNUCPARMPRELNPTIAEAJMXL ELAD EFIM ETIC EFND EFN ETLN ENGRD EWRG ETA EIN EAIRECONRP EXIMOPIC ERA ENRGJM ECONEGE ENVI ECHEVARRIA EMINETRD EAD ECONIZ EENG ELBR EWWC ELTD EAIDMG ETRK EIPR EISNLN ETEX EPTED EFINECONCS EPCS EAG ETRDKIPR ED EAIO ETRDEC ENRGPARMOTRASENVKGHGPGOVECONTSPLEAID ECONEINVEFINPGOVIZ ERNG EFINU EURFOR EWWI ELTNSNAR ETD EAIRASECCASCID EOXC ESTN EAIDAORC EAGRRP ETRDEMIN ELABPHUMSMIGKCRMBN ETRDEINVTINTCS EGHG EAIDPHUMPRELUG EAGRBTIOBEXPETRDBN EDA EPETPGOV ELAINE EUCOM EMW EFINECONEAIDUNGAGM ELB EINDETRD EMI ETRDECONWTOCS EINR ESTRADA EHUM EFNI ELABV ENR EMN EXO EWWTPRELPGOVMASSMARRBN EATO END EP EINVETC ECONEFINETRDPGOVEAGRPTERKTFNKCRMEAID ELTRN EIQ ETTW EAI ENGRG ETRED ENDURING ETTRD EAIDEGZ EOCN EINF EUPREL ENRL ECPO ENLT EEFIN EPPD ECOIN EUEAGR EISL EIDE ENRGSD EINVECONSENVCSJA EAIG ENTG EEPET EUNCH EPECO ETZ EPAT EPTE EAIRGM ETRDPREL EUNGRSISAFPKSYLESO ETTN EINVKSCA ESLCO EBMGT ENRGTRGYETRDBEXPBTIOSZ EFLU ELND EFINOECD EAIDHO EDUARDO ENEG ECONEINVETRDEFINELABETRDKTDBPGOVOPIC EFINTS ECONQH ENRGPREL EUNPHUM EINDIR EPE EMINECINECONSENVTBIONS EFINM ECRM EQ EWWTSP ECONPGOVBN
KFLO KPKO KDEM KFLU KTEX KMDR KPAO KCRM KIDE KN KNNP KG KMCA KZ KJUS KWBG KU KDMR KAWC KCOR KPAL KOMC KTDB KTIA KISL KHIV KHUM KTER KCFE KTFN KS KIRF KTIP KIRC KSCA KICA KIPR KPWR KWMN KE KGIC KGIT KSTC KACT KSEP KFRD KUNR KHLS KCRS KRVC KUWAIT KVPR KSRE KMPI KMRS KNRV KNEI KCIP KSEO KITA KDRG KV KSUM KCUL KPET KBCT KO KSEC KOLY KNAR KGHG KSAF KWNM KNUC KMNP KVIR KPOL KOCI KPIR KLIG KSAC KSTH KNPT KINL KPRP KRIM KICC KIFR KPRV KAWK KFIN KT KVRC KR KHDP KGOV KPOW KTBT KPMI KPOA KRIF KEDEM KFSC KY KGCC KATRINA KWAC KSPR KTBD KBIO KSCI KRCM KNNB KBNC KIMT KCSY KINR KRAD KMFO KCORR KW KDEMSOCI KNEP KFPC KEMPI KBTR KFRDCVISCMGTCASCKOCIASECPHUMSMIGEG KNPP KTTB KTFIN KBTS KCOM KFTN KMOC KOR KDP KPOP KGHA KSLG KMCR KJUST KUM KMSG KHPD KREC KIPRTRD KPREL KEN KCSA KCRIM KGLB KAKA KWWT KUNP KCRN KISLPINR KLFU KUNC KEDU KCMA KREF KPAS KRKO KNNC KLHS KWAK KOC KAPO KTDD KOGL KLAP KECF KCRCM KNDP KSEAO KCIS KISM KREL KISR KISC KKPO KWCR KPFO KUS KX KWCI KRFD KWPG KTRD KH KLSO KEVIN KEANE KACW KWRF KNAO KETTC KTAO KWIR KVCORR KDEMGT KPLS KICT KWGB KIDS KSCS KIRP KSTCPL KDEN KLAB KFLOA KIND KMIG KPPAO KPRO KLEG KGKG KCUM KTTP KWPA KIIP KPEO KICR KNNA KMGT KCROM KMCC KLPM KNNPGM KSIA KSI KWWW KOMS KESS KMCAJO KWN KTDM KDCM KCM KVPRKHLS KENV KCCP KGCN KCEM KEMR KWMNKDEM KNNPPARM KDRM KWIM KJRE KAID KWMM KPAONZ KUAE KTFR KIF KNAP KPSC KSOCI KCWI KAUST KPIN KCHG KLBO KIRCOEXC KI KIRCHOFF KSTT KNPR KDRL KCFC KLTN KPAOKMDRKE KPALAOIS KESO KKOR KSMT KFTFN KTFM KDEMK KPKP KOCM KNN KISLSCUL KFRDSOCIRO KINT KRG KWMNSMIG KSTCC KPAOY KFOR KWPR KSEPCVIS KGIV KSEI KIL KWMNPHUMPRELKPAOZW KQ KEMS KHSL KTNF KPDD KANSOU KKIV KFCE KTTC KGH KNNNP KK KSCT KWNN KAWX KOMCSG KEIM KTSD KFIU KDTB KFGM KACP KWWMN KWAWC KSPA KGICKS KNUP KNNO KISLAO KTPN KSTS KPRM KPALPREL KPO KTLA KCRP KNMP KAWCK KCERS KDUM KEDM KTIALG KWUN KPTS KPEM KMEPI KAWL KHMN KCRO KCMR KPTD KCROR KMPT KTRF KSKN KMAC KUK KIRL KEM KSOC KBTC KOM KINP KDEMAF KTNBT KISK KRM KWBW KBWG KNNPMNUC KNOP KSUP KCOG KNET KWBC KESP KMRD KEBG KFRDKIRFCVISCMGTKOCIASECPHUMSMIGEG KPWG KOMCCO KRGY KNNF KPROG KJAN KFRED KPOKO KM KWMNCS KMPF KJWC KJU KSMIG KALR KRAL KDGOV KPA KCRMJA KCRI KAYLA KPGOV KRD KNNPCH KFEM KPRD KFAM KALM KIPRETRDKCRM KMPP KADM KRFR KMWN KWRG KTIAPARM KTIAEUN KRDP KLIP KDDEM KTIAIC KWKN KPAD KDM KRCS KWBGSY KEAI KIVP KPAOPREL KUNH KTSC KIPT KNP KJUSTH KGOR KEPREL KHSA KGHGHIV KNNR KOMH KRCIM KWPB KWIC KINF KPER KILS KA KNRG KCSI KFRP KLFLO KFE KNPPIS KQM KQRDQ KERG KPAOPHUM KSUMPHUM KVBL KARIM KOSOVO KNSD KUIR KWHG KWBGXF KWMNU KPBT KKNP KERF KCRT KVIS KWRC KVIP KTFS KMARR KDGR KPAI KDE KTCRE KMPIO KUNRAORC KHOURY KAWS KPAK KOEM KCGC KID KVRP KCPS KIVR KBDS KWOMN KIIC KTFNJA KARZAI KMVP KHJUS KPKOUNSC KMAR KIBL KUNA KSA KIS KJUSAF KDEV KPMO KHIB KIRD KOUYATE KIPRZ KBEM KPAM KDET KPPD KOSCE KJUSKUNR KICCPUR KRMS KWMNPREL KWMJN KREISLER KWM KDHS KRV KPOV KWMNCI KMPL KFLD KWWN KCVM KIMMITT KCASC KOMO KNATO KDDG KHGH KRF KSCAECON KWMEN KRIC
PREL PINR PGOV PHUM PTER PE PREF PARM PBTS PINS PHSA PK PL PM PNAT PHAS PO PROP PGOVE PA PU POLITICAL PPTER POL PALESTINIAN PHUN PIN PAMQ PPA PSEC POLM PBIO PSOE PDEM PAK PF PKAO PGOVPRELMARRMOPS PMIL PV POLITICS PRELS POLICY PRELHA PIRN PINT PGOG PERSONS PRC PEACE PROCESS PRELPGOV PROV PFOV PKK PRE PT PIRF PSI PRL PRELAF PROG PARMP PERL PUNE PREFA PP PGOB PUM PROTECTION PARTIES PRIL PEL PAGE PS PGO PCUL PLUM PIF PGOVENRGCVISMASSEAIDOPRCEWWTBN PMUC PCOR PAS PB PKO PY PKST PTR PRM POUS PRELIZ PGIC PHUMS PAL PNUC PLO PMOPS PHM PGOVBL PBK PELOSI PTE PGOVAU PNR PINSO PRO PLAB PREM PNIR PSOCI PBS PD PHUML PERURENA PKPA PVOV PMAR PHUMCF PUHM PHUH PRELPGOVETTCIRAE PRT PROPERTY PEPFAR PREI POLUN PAR PINSF PREFL PH PREC PPD PING PQL PINSCE PGV PREO PRELUN POV PGOVPHUM PINRES PRES PGOC PINO POTUS PTERE PRELKPAO PRGOV PETR PGOVEAGRKMCAKNARBN PPKO PARLIAMENT PEPR PMIG PTBS PACE PETER PMDL PVIP PKPO POLMIL PTEL PJUS PHUMNI PRELKPAOIZ PGOVPREL POGV PEREZ POWELL PMASS PDOV PARN PG PPOL PGIV PAIGH PBOV PETROL PGPV PGOVL POSTS PSO PRELEU PRELECON PHUMPINS PGOVKCMABN PQM PRELSP PRGO PATTY PRELPGOVEAIDECONEINVBEXPSCULOIIPBTIO PGVO PROTESTS PRELPLS PKFK PGOVEAIDUKNOSWGMHUCANLLHFRSPITNZ PARAGRAPH PRELGOV POG PTRD PTERM PBTSAG PHUMKPAL PRELPK PTERPGOV PAO PRIVATIZATION PSCE PPAO PGOVPRELPHUMPREFSMIGELABEAIDKCRMKWMN PARALYMPIC PRUM PKPRP PETERS PAHO PARMS PGREL PINV POINS PHUMPREL POREL PRELNL PHUMPGOV PGOVQL PLAN PRELL PARP PROVE PSOC PDD PRELNP PRELBR PKMN PGKV PUAS PRELTBIOBA PBTSEWWT PTERIS PGOVU PRELGG PHUMPRELPGOV PFOR PEPGOV PRELUNSC PRAM PICES PTERIZ PREK PRELEAGR PRELEUN PHUME PHU PHUMKCRS PRESL PRTER PGOF PARK PGOVSOCI PTERPREL PGOVEAID PGOVPHUMKPAO PINSKISL PREZ PGOVAF PARMEUN PECON PINL POGOV PGOVLO PIERRE PRELPHUM PGOVPZ PGOVKCRM PBST PKPAO PHUMHUPPS PGOVPOL PASS PPGOV PROGV PAGR PHALANAGE PARTY PRELID PGOVID PHUMR PHSAQ PINRAMGT PSA PRELM PRELMU PIA PINRPE PBTSRU PARMIR PEDRO PNUK PVPR PINOCHET PAARM PRFE PRELEIN PINF PCI PSEPC PGOVSU PRLE PDIP PHEM PRELB PORG PGGOC POLG POPDC PGOVPM PWMN PDRG PHUMK PINB PRELAL PRER PFIN PNRG PRED POLI PHUMBO PHYTRP PROLIFERATION PHARM PUOS PRHUM PUNR PENA PGOVREL PETRAEUS PGOVKDEM PGOVENRG PHUS PRESIDENT PTERKU PRELKSUMXABN PGOVSI PHUMQHA PKISL PIR PGOVZI PHUMIZNL PKNP PRELEVU PMIN PHIM PHUMBA PUBLIC PHAM PRELKPKO PMR PARTM PPREL PN PROL PDA PGOVECON PKBL PKEAID PERM PRELEZ PRELC PER PHJM PGOVPRELPINRBN PRFL PLN PWBG PNG PHUMA PGOR PHUMPTER POLINT PPEF PKPAL PNNL PMARR PAC PTIA PKDEM PAUL PREG PTERR PTERPRELPARMPGOVPBTSETTCEAIRELTNTC PRELJA POLS PI PNS PAREL PENV PTEROREP PGOVM PINER PBGT PHSAUNSC PTERDJ PRELEAID PARMIN PKIR PLEC PCRM PNET PARR PRELETRD PRELBN PINRTH PREJ PEACEKEEPINGFORCES PEMEX PRELZ PFLP PBPTS PTGOV PREVAL PRELSW PAUM PRF PHUMKDEM PATRICK PGOVKMCAPHUMBN PRELA PNUM PGGV PGOVSMIGKCRMKWMNPHUMCVISKFRDCA PBT PIND PTEP PTERKS PGOVJM PGOT PRELMARR PGOVCU PREV PREFF PRWL PET PROB PRELPHUMP PHUMAF PVTS PRELAFDB PSNR PGOVECONPRELBU PGOVZL PREP PHUMPRELBN PHSAPREL PARCA PGREV PGOVDO PGON PCON PODC PRELOV PHSAK PSHA PGOVGM PRELP POSCE PGOVPTER PHUMRU PINRHU PARMR PGOVTI PPEL PMAT PAN PANAM PGOVBO PRELHRC

Browse by classification

Community resources

courage is contagious

Viewing cable 08LUSAKA44, Zambia Power Generation Update-Light at the End of the

If you are new to these pages, please read an introduction on the structure of a cable as well as how to discuss them with others. See also the FAQs

Understanding cables
Every cable message consists of three parts:
  • The top box shows each cables unique reference number, when and by whom it originally was sent, and what its initial classification was.
  • The middle box contains the header information that is associated with the cable. It includes information about the receiver(s) as well as a general subject.
  • The bottom box presents the body of the cable. The opening can contain a more specific subject, references to other cables (browse by origin to find them) or additional comment. This is followed by the main contents of the cable: a summary, a collection of specific topics and a comment section.
To understand the justification used for the classification of each cable, please use this WikiSource article as reference.

Discussing cables
If you find meaningful or important information in a cable, please link directly to its unique reference number. Linking to a specific paragraph in the body of a cable is also possible by copying the appropriate link (to be found at theparagraph symbol). Please mark messages for social networking services like Twitter with the hash tags #cablegate and a hash containing the reference ID e.g. #08LUSAKA44.
Reference ID Created Released Classification Origin
08LUSAKA44 2008-01-14 06:18 2011-08-30 01:44 UNCLASSIFIED//FOR OFFICIAL USE ONLY Embassy Lusaka
VZCZCXRO0943
RR RUEHBZ RUEHDU RUEHJO RUEHMR RUEHRN
DE RUEHLS #0044/01 0140618
ZNR UUUUU ZZH
R 140618Z JAN 08
FM AMEMBASSY LUSAKA
TO RUEHC/SECSTATE WASHDC 5310
INFO RUCNSAD/SOUTHERN AF DEVELOPMENT COMMUNITY COLLECTIVE
RUCPDOC/DEPT OF COMMERCE WASHDC
RHEBAAA/DOE WASHDC
UNCLAS SECTION 01 OF 02 LUSAKA 000044 
 
SIPDIS 
 
SIPDIS 
SENSITIVE 
 
DEPARTMENT FOR AF/S 
COMMERCE FOR 4510/ITA/IEP/ANESA/OA 
 
E.O. 12958: N/A 
TAGS: ENRG EINV BTIO ZA
SUBJECT: Zambia Power Generation Update-Light at the End of the 
Tunnel? 
 
Ref: 07 Lusaka 903 
 
1. (SBU) Summary and introduction. Zambia's installed power 
generating capacity is 1640 megawatts (MW), and consists almost 
entirely of hydroelectric power.  Ongoing rehabilitation projects 
reduce actual generating capacity to 1200 MW for the near future, 
which is well below estimated peak demand of about 1600 MW for 2008. 
 As a result, increasing power outages are likely in 2008-2009.   By 
late 2009, thanks to rehabilitation and expansion projects, actual 
generating capacity should increase to 1850 MW.   New hydropower 
projects being developed by Chinese, Indian, and Canadian firms 
together with Zambian partners experienced past delays and currently 
are expected to be commissioned in 2012 and 2013.  The new projects 
should increase generating capacity to over 3000 MW and help Zambia 
be a net exporter in the region--but some projects might face 
possible delays.  End summary and introduction. 
 
Background: Plans to Keep Up With Demand -- Not Enough, Yet 
 
2. (SBU) Zambia's power generating capacity has not increased 
significantly in many years, but capacity-expanding efforts that 
started in the late 1990s should finally be paying off in upcoming 
years.  To improve national power generating capacity, in the late 
1990s, the Government of Zambia opted to take a "three-pronged" 
approach, Mr. Israel Phiri, Director of the Office for Promoting 
Private Power Investment (OPPPI) which was set up in 1999 in the 
Ministry of Energy and Water Development, told Emboffs.  The first 
tactic was for ZESCO to rehabilitate its major hydroelectric plants, 
which were not producing at full capacity due to a prolonged lack of 
maintenance.  The World Bank and other donors helped to support 
these efforts, which progressed slowly and were not completed by the 
targeted 2007 timeframe.  Rehabilitation of the 108 MW Victoria 
Falls hydro power station is already complete, while rehabilitation 
work is continuing at Kafue Gorge (900 MW installed capacity) and 
Kariba North Bank (600 MW installed capacity).  The work involves 
shutting down sections of each power station-300 MW at Kafue Gorge 
and 150 MW at Kariba-over a 13-month period.  The 450 MW shortfall 
means actual power production is well below installed capacity, and 
explains significant load shedding in the recent past.  Phiri 
expects the rehabilitation work to be completed by the end of 2008 
or in early 2009. 
 
3. (U) The GRZ's second approach was to "uprate" or expand the 
capacity of existing power stations.  Phiri said that at a cost of 
about USD 100 million, ZESCO is adding 90 MW of generating capacity 
at Kafue Gorge and 120 MW at Kariba North Bank, adding a total of 
210 MW to current power generating capacity.  The slow-moving 
expansion projects are now expected to be completed by 2009, and 
will bring Zambia's generating capacity to 1850 MW. 
 
4. (SBU) As of late 2007, ZESCO's actual power generation output 
stood at approximately 1200 MW, reflecting total installed capacity 
of 1640 MW, minus 450 MW that is shut down for rehabilitation. 
During periods when demand exceeds 1200 MW (ZESCO currently 
estimates that peak demand will be about 1600 MW or more -- the new 
Lumwana Copper Mine and Konkola Deep Copper Mine are expected to add 
120 MW and 150 MW of demand in 2008, respectively) and imported 
power from South Africa, Zimbabwe, or the Democratic Republic of 
Congo is not available, more "load-shedding," as power outages and 
brownouts are widely referred to here, appears inevitable. 
 
New Hydroelectric Power Projects in Development 
 
5. (SBU) The final focus of the GRZ's three-pronged approach was to 
develop entirely new projects, as public-private partnerships, to 
tap Zambia's enormous potential for hydro-electric power, estimated 
at between 6000 to 8000 MW.  The GRZ issued international tenders 
for three major hydropower projects, Kariba North Bank, Kafue Gorge 
and Itezhi-Tezhi, and shortlisted bidders in 2001.  U.S.-based AES 
was active in one of the shortlisted bidder consortia, but according 
to Mr. Phiri, in 2002 it pulled out of many sub-Saharan African 
projects, including in Zambia, after encountering problems with a 
project in Uganda. 
 
6. (SBU) After all three qualified bidder groups withdrew bids for 
the hydropower projects, the GRZ opted for other, non-competitive 
means to finalize the deals, in the interest of moving quickly, 
Phiri explained to Emboffs.  Some of the projects remained with 
OPPPI and others became the responsibility of ZESCO.  The GRZ used a 
2003 visit by President Mwanawasa to China to promote the projects, 
and China agreed to take on the Kariba North Bank Extension project 
(and for a while, the GRZ was discussing the Kafue Gorge Lower 
project with China as well).  A high-level delegation visiting from 
Iran in 2003 also indicated an interest and capability in 
hydro-electric, which resulted in a deal for the development of 
Itezhi-Tezhi.  However, in following years, Iran pressured the GRZ 
 
LUSAKA 00000044  002 OF 002 
 
 
to side with it on sensitive issues in the UN.  According to both 
Phiri and Aaron Nyirenda, Director for Power Generation Projects at 
ZESCO, the GRZ decided to pull out of the deal--when the project was 
at the pre-design stage and discussions on financing were already 
underway--so the Iranians would not use the project for political 
leverage.   ZESCO worked with the World Bank to hold a power sector 
investor workshop in May 2006, and numerous companies expressed an 
interest.  However, only India's Tata actively followed up, which 
resulted in a deal.  According to Nyirenda, ZESCO and Tata have set 
up a 50-50 percent joint venture company to oversee the project, 
with the GRZ receiving one "golden share."  The Itezhi-Tezhi 
hydropower project is valued at USD 150 million and is expected to 
produce 120 MW by 2012. 
 
7. (SBU) Following extensive feasibility studies and negotiations, 
in November 2007, ZESCO and China's Sinohydro signed a USD 243 
million contract for the engineering, procurement and construction 
of the Kariba North Bank Extension hydropower project of 360 MW, and 
in December, ZESCO finalized a concessional loan agreement with the 
Chinese Export-Import Bank, according to Nyirenda.  The project is 
supposed to begin in 2008 and be commissioned by 2012. 
 
8. (SBU) The GRZ had been in discussions with Sinohydro over 
development of the Kafue Gorge Lower project, Phiri told Emboffs, 
but after both sides failed to reach agreement, OPPPI started to 
work to re-tender the project with advice from the International 
Finance Corporation, which will help cover the costs of feasibility 
studies for an alternate project site, "Site Five," about six 
kilometers from the original site proposed.  The original project 
size, 600 MW of power generating capacity, could increase to as much 
as 750 MW at the new site, Phiri said.  He expects the next phase of 
feasibility studies to be carried out starting in March 2008.  OPPPI 
will be ready to solicit bids by the end of 2008.  OPPPI plans to 
award the project in 2009, with commissioning by 2013. 
 
9. (SBU) Phiri told Emboffs that the planned Kalungwishi hydropower 
project in Luapula Province involves two stations totaling 218 MW of 
power generating capacity as well as installation of 500 kilometers 
of transmission line to link to the national grid, in Kasama and 
Serenje.  OPPPI is still negotiating with the selected bidder, 
Lunzuwa Power Authority, which is a subsidiary of local firm Olympic 
Milling and aligned with a Canadian firm with solid hydroelectric 
experience, Knight-Piesold.  Assuming that final details can be 
agreed upon, the bidder will need to arrange financing for the 
project during 2008.  Phiri expects construction to begin in 2009 
and commissioning to take place in 2013. 
 
Looking Beyond Hydropower Resources -- Not Much To See 
 
10. (U) In order to diversify its sources of electric power, Phiri 
told Emboffs that OPPPI was exploring options for developing about 
500 MW of thermal power generating capacity, to come on line by 
2013, but had not reached any decisions yet.  Nyirenda noted that 
both diesel and coal powered turbines would be comparatively 
expensive to operate in Zambia, given the high cost of the 
feedstock.  (Note: In fact, ZESCO's Director of Engineering 
Development Alvin Monga also told the media in late December 2007 
that ZESCO would phase out the use of several small diesel 
generators that supply electricity in five districts, because of the 
high cost of fuel and operating losses from running the generators. 
End note.)  Neither our OPPPI nor ZESCO sources could foresee 
Zambia's turning to nuclear energy as an option for diversifying 
electricity supply. 
 
11. (SBU) Comment:  If completed on schedule, by 2013, the four new 
hydropower projects would add 1510 MW of power to the national grid, 
bringing Zambia's generating capacity to 3360 MW and enabling it to 
become a regional electricity exporter.  After years of delays, the 
Itezhi-Tezhi and Kariba North Bank Extension projects both appear to 
be on track and moving forward at a steady pace.  However, there 
might be challenges ahead for OPPPI as it proceeds with the massive 
Kafue Gorge Lower project.  It appears that senior levels of the 
Zambian government might have other ideas for the project -- the 
Executive Chairman of Copperbelt Energy Corporation told Emboffs in 
late December that CEC had teamed up with copper mining company 
Mopani, owned by Glencore, to propose developing the Kafue Gorge 
Lower project to senior GRZ officials, who were very receptive to 
the concept.  The GRZ might welcome the opportunity for a 
Zambian-controlled company to take on such a high-profile project, 
although side-stepping a competitive tender process could result in 
less attractive terms for the deal. 
 
KOPLOVSKY